Analysis of Causes for Extension of Time in Construction Projects: A Case Study of Kageshwori Manohara Municipality

Authors

  • Sunil Nepal Center for Post Graduate Studies, Nepal Engineering College (Affiliated to Pokhara University), Prayag Pokhari, Lagankhel, Nepal
  • Subash Kumar Bhattarai Lead-Health, Infrastructure and Policy, HERD International, Kathmandu, Nepal
  • Dinesh Sukamani Center for Post Graduate Studies, Nepal Engineering College (Affiliated to Pokhara University), Prayag Pokhari, Lagankhel, Nepal
  • Sujan Nepal Center for Post Graduate Studies, Nepal Engineering College (Affiliated to Pokhara University), Prayag Pokhari, Lagankhel, Nepal

DOI:

https://doi.org/10.3126/kjem.v4i1.74707

Keywords:

RI Index, Projects Delay, Multivariate Statistics, Eigenvalues Scaling

Abstract

Extension of Time (EoT) claims are a common occurrence in construction projects worldwide, often leading to disputes due to insufficient attention to delay causes during the contract initiation phase. However, in the context of Kageshwori Manohara Municipality, these challenges are particularly pronounced due to localized factors. This study identifies key causes of EoT through qualitative and quantitative analyses, utilizing Principal Component Analysis (PCA), Kaiser-Meyer-Olkin (KMO) testing, Bartlett's Test of Sphericity, Eigenvalue and variance analysis, and reliability assessments using Cronbach's Alpha. Principal Component Analysis (PCA) helped to categorize twelve major EoT causes into three components: Design and Consultant-Related Issues (Eigenvalue: 13.892, Variance: 55.57%), Project Management and Execution Challenges (Eigenvalue: 1.146, Variance: 4.58%), and External and Unforeseen Conditions (Eigenvalue: 1.000, Variance: 4.00%). Significant causes include inadequate design information, poor project management, and unforeseen challenges like land acquisition disputes. These causes were ranked using the Relative Importance Index (RII) to prioritize their impacts on project time extensions. The authors believe that present findings illuminate the need for improved design and planning processes, along with adaptive project management practices to mitigate EoT claims and enhance project performance within the municipality.

Downloads

Download data is not yet available.
Abstract
42
PDF
27

Downloads

Published

2025-02-06

How to Cite

Nepal, S., Kumar Bhattarai, S., Sukamani, D., & Nepal, S. (2025). Analysis of Causes for Extension of Time in Construction Projects: A Case Study of Kageshwori Manohara Municipality. Kathford Journal of Engineering and Management, 4(1), 59–72. https://doi.org/10.3126/kjem.v4i1.74707

Issue

Section

Journal