Assessment of the Cause of Variation and Extension of Time in Water Supply Projects

Authors

  • Mohan Regmi School of Engineering, Faculty of Science and Technology, Pokhara University, Pokhara, Nepal
  • Rajib Pokhrel School of Engineering, Faculty of Science and Technology, Pokhara University, Pokhara, Nepal

DOI:

https://doi.org/10.3126/oodbodhan.v9i1.95666

Keywords:

Variation Order, Extension of Time, Water Supply Projects, Relative Importance Index, Severity Index

Abstract

Public water supply projects in Nepal frequently face cost overruns and schedule delays. It mostly investigates the causes and extent of Variation Orders (VO) and Extensions of Time (EOT) in water supply projects implemented under the Department of Water Supply and Sewerage Management (DWSSM) in Gandaki Province, Nepal. Primary data were collected through questionnaires from clients, contractors, and water user committees, while secondary data were obtained from EOT and VO approval reports. Relative Importance Index (RII) and Severity Index (SI) were used to rank and prioritize the causes of VO and EOT. Among 25 identified causes, inadequate coordination among stakeholders with RII 0.785 and communication delay from the project manager with SI 78.889 were found to be the most significant causes of EOT. It reflected different ranking orders using different tools. Similarly, among 13 identified causes of VO, mistakes in the bill of quantities with RII 0.852 and incomplete design with SI 85.185 were the most influential causes of VO. Spearman’s rho correlation analysis showed a strong positive correlation between the causes of VO and EOT, with a correlation coefficient of 0.805 and a significance value of p = 0.000 (<0.01). The Kruskal-Wallis test confirmed that all respondent groups shared similar perceptions regarding these causes. Reliability tests yielded Cronbach’s alpha values above 0.8, validating the internal consistency of the survey data. Improper communication among the stakeholders and technical errors in designing and quantifying the quantities were the major causes of the water supply project delay and variation.

Downloads

Download data is not yet available.
Abstract
6
PDF
2

Downloads

Published

2026-06-12

How to Cite

Regmi, M., & Pokhrel, R. (2026). Assessment of the Cause of Variation and Extension of Time in Water Supply Projects. OODBODHAN, 9(1), 174–188. https://doi.org/10.3126/oodbodhan.v9i1.95666

Issue

Section

Articles